Overview


Safety Training offers more than 100+ courses in the Health and Safety Industry in the UK.

After acquisition to a larger company, the CEO expanded their operations to Africa setting up offices in South Africa, Nigeria and Kenya providing safety training and supply of equipment.

The Kenyan team was responsible for handing the digital space, email marketing and web development,

Non Disclosure Agreement


To protect the clients intellectual property, I excluded the visuals and focused on the process as well as lessons learnt from the the project.

Problem


Management was keen on implementing an internal system that would assist with increasing efficiency within the administration team.

Delegate bookings turnaround was extremely slow and the delegates themselves were having a tough time getting through or feedback from the administrators.

Frustrations led delegates to competitors and that meant losing business which affected the sales and the bottom line for the company.

Solution


The existing system had an API that we could build the desired solution and solve the problem the business was facing.

The Head of Sales and Technical/Operations Director presented a flow chart of how they would like the system to run and my job as project manager was to come up with a Software Requirement Document with timelines.

Broke down the project into Event based deliverables so as to make it manageable since it was myself and the backend developer.

Lessons


Reflecting on what we did on the projects and the mistakes made , I am happy to say that the project was delivered successfully. Knowing what I know now, If I were to receive a similar brief, I would approach it differently. I would

Focus on prototyping an MVP

We were already constrained and despite preparing a development plan the management teams had conflicting interpretation and ideas.

The biggest lesson I learnt from this experience was before touching any code or writing any specification for the software, Clarify Clarify. Clarify. Never assume.

It seems obvious but when the client, herein the boss, insists on the urgency to ship or deliver, it doesn't hurt to take some time to clarify.

The best way I have found out to validate is through a Lo-Fi prototype and involving them on each sprint & design decisions.

Project Management Methodology

I thought I was being agile but in retrospect the executed the project traditionally, I accept the responsibility to not step up and control the project as much as I should and let most of the decisions be made by non technical herein management.

Despite creating a project plan and allocating the man hours to take on the project, I should have taken it a step further and ensured to request for additional personnel to deliver the project as per the stated time.

Constraints & Stack Decisions

Next mistake I made was being fixed with the process and not taking into consideration what the project development requirements were. I overly depended on the developers exertise which meant being super exposed to his limitations on delivery.

For example. The project was written procedurally and didn't rely on frameworks. If I was to take another stub at the projects, I would pick a microservice architecture over the two-tier architecture so as to allow developers to focus on a single service rather than looking at the entire application.

By approaching it from a microservice angle, it allows bandwidth to develop, test, deploy and allow room to scale and switch to new technologies easily without affecting the whole system and project.

Role


Project Management

UX/UI Design

Front End Developer

Duties


Flowchart

UX/UI Design

Front End Developer

Tools & Technologies: Who did I work with?


Webflow

TailwindCSS

PHP

Stakeholders: Who did i work with?


CEO

Head of Sales

Technical / Operations Director

Country Directors

Backend Developer